June 5th, 2023 - Clubhouse's Construction Continues - Rough HVAC

Darren's guys from Ken's Confort Zone Air Conditioning came today to do the rough HVAC install. Once the construction is further along, they will come back to finish.

May 29th, 2023 - Clubhouse's Construction Continues - Roof

Brad's guys installed the new metal roof on the clubhouse and tied it up to the old/existing roof on the community pavilion.

May 18th, 2023 - Clubhouse's Construction Continues - Plumbing

David and his guys from Hassell Free Plumbing came back to install the PEX water lines and PVC drain and vent pipes.

May 17th, 2023 - Clubhouse's Construction Continues - Windows

The windows have been installed. We are still waiting on the doors to be delivered so that they, too, can be installed. When that is done (along with the roof), the building will be weather safe.

May 16th, 2023 - Clubhouse's Construction Continues - Roof Decking

The roof decking has been installed, and a corresponding section of the old roof has been removed to allow for the merger with the new roof.

May 15th, 2023 - Clubhouse's Construction Continues - Siding

We are very pleased with the progress that Brad's team has had. Today, the siding has been installed, the windows have been delivered, and the doors have been scheduled for delivery in the next couple of days.

May 12th, 2023 - Clubhouse's Construction Continues - Wall Framing is Complete

In just one week, Brad's guys finished the framing of the structure. Even the house wrap has been installed.

May 5th, 2023 - Clubhouse's Construction Continues - Wall Framing Commences

The rain is good for the lake levels, but it sure is not good for construction. After several delays caused by the never ending rain, Brad's team has managed to get the wood material delivered this week and started framing the walls today.

April 4th, 2023 - Clubhouse's Construction Continues - Concrete Foundation

Despite the many days of rain lately, Brad's team has managed to get the concrete forms ready over the last few days, and they just poured the concrete foundation today.

March 20th, 2023 - Clubhouse's Construction Continues - Rough Plumbing

We are so happy of the progress at which Brad and his contractors are moving. Today, Brad sent his plumber, David Hussell and his guys from Hassell Free Plumbing to do the rough plumbing at the clubhouse.

March 13th, 2023 - Clubhouse's Construction Begins

We are happy to announce that the construction of the clubhouse/gym has begun. With the money that has been raised so far, the board elected to start the build of the clubhouse. We didn’t want the money to sit in the bank not earning any considerable interest, while inflation was eroding our purchasing power. Therefore, instead of waiting till after we raise all the money in 2024 and build afterwards, we decided to use the money we already have collected to build the clubhouse structure itself. We still will need to wait for the 2024 special assessment to finish the whole project. So this week, our contractor, Brad Gilmore, brought his first contractor, Outlaw Excavations & Land Management, and did the site prep. We look forward to working with Brad on this exciting project.

February 2023 - More Road Repairs

Edgewater's 6-year-old roads are needing more repairs. One section on Edgewater Drive, two sections on West Shoreline Drive, and 5 sections on Southern Shore Court had gotten so bad, it was almost impossible to drive across them. Therefore, our asphalt contractor was hired to sawcut all of the holes and bad sections in the affected areas, remove the existing damaged asphalt and 4” of existing dirt subgrade, grade and compact existing subgrade, install and compact 3” of concrete Flex Base (TxDot Item 247), apply Tack coat adhesive to adjacent asphalt edges to assure bonding of new and old asphalt, and finally install 3” of Type D surface course asphalt hot mix compacted to manufactures specifications.

January 2023 - Internet Tower has been Installed

NextLink has finished all the permits with the electric company, the county, and the fire marshal. Therefore, they just sent their tower as well as a crane to install it. We hope that in the next few weeks, the electric components will be connected and the radio transmitters will be installed.